## Overview
NETWORKDAYS is a function of the Date and Time category that calculates the number of working days between two dates, excluding weekends (Saturday and Sunday by default) and optionally specified holidays.
## Usage
### Syntax
**NETWORKDAYS(start_date, end_date, [holidays]) => workdays**
### Argument descriptions
* *start_date* ([number](/features/value-types#numbers), required). The start date expressed as a [serial number](/features/serial-numbers.md).
* *end_date* ([number](/features/value-types#numbers), required). The end date expressed as a [serial number](/features/serial-numbers.md).
* *holidays* ([array](/features/value-types#arrays) or [range](/features/value-types#ranges), optional). A list of dates to exclude from the calculation, expressed as serial numbers.
### Additional guidance
- If the supplied _start_date_ and _end_date_ arguments have fractional parts, NETWORKDAYS uses their [floor values](https://en.wikipedia.org/wiki/Floor_and_ceiling_functions).
- If _start_date_ is later than _end_date_, the function returns a negative number.
- Weekend days are Saturday and Sunday by default. Use [NETWORKDAYS.INTL](networkdays.intl) for custom weekend definitions.
- Empty cells in the _holidays_ array are ignored.
- The calculation includes both the start and end dates if they are workdays.
### Returned value
NETWORKDAYS returns a [number](/features/value-types#numbers) representing the count of working days between the two dates.
### Error conditions
* In common with many other IronCalc functions, NETWORKDAYS propagates errors that are found in its arguments.
* If fewer than 2 or more than 3 arguments are supplied, then NETWORKDAYS returns the [`#ERROR!`](/features/error-types.md#error) error.
* If the *start_date* or *end_date* arguments are not (or cannot be converted to) [numbers](/features/value-types#numbers), then NETWORKDAYS returns the [`#VALUE!`](/features/error-types.md#value) error.
* If the *start_date* or *end_date* values are outside the valid date range, then NETWORKDAYS returns the [`#NUM!`](/features/error-types.md#num) error.
* If the *holidays* array contains non-numeric values, then NETWORKDAYS returns the [`#VALUE!`](/features/error-types.md#value) error.
## Details
IronCalc utilizes Rust's [chrono](https://docs.rs/chrono/latest/chrono/) crate to implement the NETWORKDAYS function. The function treats Saturday and Sunday as weekend days.
## Examples
[See some examples in IronCalc](https://app.ironcalc.com/?example=networkdays).
## Links
* See also IronCalc's [NETWORKDAYS.INTL](/functions/date_and_time/networkdays.intl.md) function for custom weekend definitions.
* Visit Microsoft Excel's [NETWORKDAYS function](https://support.microsoft.com/en-us/office/networkdays-function-48e717bf-a7a3-495f-969e-5005e3eb18e7) page.
* Both [Google Sheets](https://support.google.com/docs/answer/3093018) and [LibreOffice Calc](https://wiki.documentfoundation.org/Documentation/Calc_Functions/NETWORKDAYS) provide versions of the NETWORKDAYS function.